Alignment of Bengaluru's Tunnel road

Bengaluru’s Tunnel Road tender gets fourth extension amid design revisions

Bengaluru: 

The tender submission deadline for Bengaluru’s ambitious 16.75-km North–South Tunnel Road project has been extended for the fourth time, marking yet another delay in the city’s most high-profile traffic decongestion initiative.

In a fresh Corrigendum-07, issued by Bengaluru Smart Infrastructure Limited (BSIL), the new deadline for bid submission has been extended from October 31, 2025, to November 15, 2025.

The ₹17,800-crore project proposes twin-tube underground corridors linking Hebbal and Central Silk Board, with 16 entry and exit ramps. Envisioned under a Public-Private Partnership (PPP) model, the government expects 60% private investment.

Officials said the latest extension follows “requests from participating bidders” who sought additional time to finalise their submissions, reflecting ongoing interest from large infrastructure firms despite the project’s complexity.

Timeline of Tender Extensions

Corrigendum No.Original / Previous DeadlineRevised DeadlineDate of Issuance
Corrigendum-01June 30, 2025July 15, 2025June 2025
Corrigendum-02July 15, 2025August 10, 2025July 2025
Corrigendum-04August 10, 2025September 20, 2025August 2025
Corrigendum-07 (current)October 31, 2025November 15, 2025November 2025

(Based on official updates from Bengaluru Smart Infrastructure Ltd)

Despite multiple deadline extensions, the tunnel road continues to remain a contentious yet closely watched project, with debates over its feasibility, environmental cost, and funding structure.